Minor Heads  Variations Between
of Demand Budget 2005-06 A.R. 2005-06 AR & BG % BETN  ACT EXP END % of Exp booked  
AR & BG OF JULY 2005 to end of July'05
          WRT BG
11 New Lines (C)
CAP 15,00,00 42,05,91 27,05,91 180.39 24514.28 16.34
Total 15,00,00 42,05,91 27,05,91 180.39 24514.28 16.34
15 Doubling
CAP 0 -20 -20
DF3 0 0 0
Total DF 0 0 0
Total 0 -20 -20
16 Traffic facilities-Yard remodelling & Others
CAP 2,17,72 1,00,30 -1,17,42 -53.93 5001.02 22.97
DRF 0 29,91 29,91
DF1 23,00,71 22,87,22 13,49 0.59 15397.29 6.69
DF2 0 0 0
DF3 0 0 0
DF4 0 0 0
Total DF 23,00,71 22,87,22 ,13,49 0.59 15397.29
OLWR 0 0 0 57.45
Total 25,18,43 24,17,43 -1,01,00 -4.01 2,04,56 8.12
17 Computerisation 46,01,42
CAP 1,50,00 6,58 -1,43,42 -95.61 306.99 2.05
DRF 0 1 1
DF1 2,95,90 49,33 -2,46,57 -83.33 2473.74 8.36
DF2 0 0 0
DF3 0 0 0
Total DF 2,95,90 49,33 -2,46,57 -83.33 2473.74
OLWR 5,00 3,34 -1,66 -33.20
Total 4,50,90 ,59,26 -3,91,64 -86.86 ,27,81 6.17
21a. Locomotives
CAP 1,22,94 2,95,68 1,72,74 140.51 13169.17 107.12
DRF 4,17,05 2,99,32 -1,17,73 -28.23
DF3 0 0 0
Total DF 0 0 0
SRSF 0 0 0 13185
Total 5,39,99 5,95,00 55,01 10.19 26354.17 48.80
21b. Carriages
CAP 50,00 50,00 0 0.00
DRF 0 0 0
SRSF 0 0 0
Total 50,00 50,00 0 0.00
21c. Wagons
CAP 0 0 0 14425.6
DRF 0 0 0 34452.54
SRSF 0 0 0
Total 0 0 0 48878.14
21d. Track Machines
CAP 0 0 0
Total 0 0 0
21 Rolling Stock(Total)
CAP 1,72,94 3,45,68 1,72,74 99.88 27594.77 159.56
DRF 4,17,05 2,99,32 -1,17,73 -28.23 34452.54 82.61
DF3 0 0 0
Total DF 0 0 0
SRSF 0 0 0 13185
Total 5,89,99 6,45,00 55,01 9.32 7,52,32 127.51
29 Road Safety Works-Level Crossings.
SF 15,55,02 13,34,22 -2,20,80 -14.20 14014.93 9.01
Total 15,55,02 13,34,22 -2,20,80 -14.20 14014.93 9.01
30 Road Safety Works-Road Over/Under Bridges.
SF 4,75,00 6,51,85 1,76,85 37.23 3105.85 6.54
Total 4,75,00 6,51,85 1,76,85 37.23 3105.85 6.54
31 Track Renewals
DRF 167,00,00 212,49,27 45,49,27 27.24 537582.48 32.19
DF4 0 0 0
Total DF 0 0 0
SRSF 103,00,00 73,30,36 -29,69,64 -28.83 259325.07 25.18
Total 270,00,00 285,79,63 15,79,63 5.85 796907.55 29.52
32 Bridge Works
DRF 3,34,98 9,01,92 5,66,94 169.25 39870.15 119.02
DF1 33 0 -33 -100.00
DF2 0 0 0
Total DF 33 0 -33 -100.00
SRSF 34,14,54 13,82,00 -20,32,54 -59.53 83811.46 24.55
OLWR 0 3,00 3,00 181.42
Total 37,49,85 22,86,92 -14,62,93 -39.01 123863.03 33.03
33 Signalling and Telecommunication Works
CAP 5,00 5,00 0 0.00
DRF 31,94 5,13,21 4,81,27 ###### 11459.33 358.78
DF1 4,06,00 20,64,58 16,58,58 408.52 7817.08 19.25
DF2 0 0 0
DF3 0 0 0
DF4 0 0 0
Total DF 4,06,00 20,64,58 16,58,58 408.52 ,78,17 19.25
SRSF 34,91,50 34,91,50 0 0.00 88281.99 25.28
OLWR 5,00 6,90 1,90 38.00
Total 39,39,44 60,81,19 21,41,75 54.37 10,75,58 27.30
36 Other Electrical Works
CAP 36,00 61,50 25,50 70.83 400.7 11.13
DRF 3,27,51 5,33,25 2,05,74 62.82 1339.1 4.09
DF1 1,54,00 3,99,24 2,45,24 159.25 1558.56 10.12
DF2 0 0 0
DF3 0 0 0
DF4 0 0 0
Total DF 1,54,00 3,99,24 2,45,24 159.25 1558.56 10.12
OLWR 9,00 9,00 0 0.00 282.71 31.41
Total 5,26,51 10,02,99 4,76,48 90.50 3581.07 6.80
41 Machinery & Plant
CAP 1,10,00 2,30,09 1,20,09 109.17 1499.85 13.64
DRF 2,48,32 6,09,43 3,61,11 145.42 2386.68 9.61
DF1 83,00 1,45,35 62,35 75.12 750.46 9.04
DF2 0 0 0
DF3 0 0 0
DF4 0 0 0
Total DF 83,00 1,45,35 62,35 75.12 750.46 9.04
SRSF 5,16,44 5,16,44 0 0.00 301611.02 584.02
OLWR 28,00 2,07,50 1,79,50 641.07 1470.16 52.51
Total 9,85,76 17,08,81 7,23,05 73.35 30,77,18 312.16
42 Workshops including Production Units
CAP 37,90 4,21,93 3,84,03 ###### 1677.85 44.27
DRF 4,00 8,32 4,32 108.00 243.42 60.86
DF1 5,56,21 12,56,94 7,00,73 125.98 9981.15 17.94
DF2 0 0 0
DF3 0 0 0
DF4 0 0 0
Total DF 5,56,21 12,56,94 7,00,73 125.98 9981.15 17.94
OLWR 1,13 14,40 13,27 ###### 277.94 245.96
Total 5,99,24 17,01,59 11,02,35 183.96 12180.36 20.33
51 Staff Quarters
CAP 32,38 1,02,82 70,44 217.54 1683.28 51.99
DRF 71,93 1,58,52 86,59 120.38 2774.47 38.57
Total 1,04,31 2,61,34 1,57,03 150.54 4457.75 42.74
52 Amenities for Staff
CAP 7,00 59,20 52,20 745.71 1218.84 174.12
DRF 4,50 29,52 25,02 556.00
DF1 57,39 1,86,60 1,29,21 225.14 3630.98 63.27
DF2 0 0 0
Total DF 57,39 1,86,60 1,29,21 225.14 3630.98 63.27
OLWR 0 0 0 9.96
Total 68,89 2,75,32 2,06,43 299.65 4859.78 70.54
53 Passengers Amenities
DRF 17,00 68,00 51,00 300.00 1778.72 104.63
DF1 3,57,96 7,84,54 4,26,58 119.17 26691.51 74.57
DF2 0 0 0
DF3 0 0 0
DF4 0 0 0
Total DF 3,57,96 7,84,54 4,26,58 119.17 26691.51 74.57
OLWR 5,00 11,67 6,67 133.40
Total 3,79,96 8,64,21 4,84,25 127.45 28470.23 74.93
64 Other specified works
CAP 3,63,00 8,80,22 5,17,22 142.48 13481.23 37.14
DRF 10,00 48,93 38,93 389.30 365 36.50
DF1 5,19,16 15,11,42 9,92,26 191.13 10401.59 20.04
DF2 0 0 0
DF3 0 0 0
DF4 0 0 0
Total DF 5,19,16 15,11,42 9,92,26 191.13 10401.59 20.04
OLWR 2,33 3,78 1,45 62.23 298.81 128.24
Total 8,94,49 24,44,35 15,49,86 173.27 24546.63 27.44
71 Stores Suspense
CAP 419,28,80 506,74,81 87,46,01 20.86 3474469.9 82.87
Total 419,28,80 506,74,81 87,46,01 20.86 3474469.9 82.87
72 Manufacture Suspense
CAP 122,76,07 119,21,21 -3,54,86 -2.89 402467.32 32.78
Total 122,76,07 119,21,21 -3,54,86 -2.89 402467.32 32.78
73 Miscellaneous Advances
CAP 0 0 0
Total 0 0 0
Total (Voted+Charged)
CAP 568,36,81 692,58,11 ######## 21.61 3954316 69.57
DRF 181,67,23 244,49,61 62,82,38 34.58 63,22,52 34.80
DF1 47,30,66 86,85,22 39,81,54 84.16 7,87,02 16.64
DF2 0 0 0
DF3 0 0 0
DF4 0 0 0
Total DF 47,30,66 86,85,22 39,81,54 84.16 78702 16.64
SF 20,30,02 19,86,07 -,43,95 -2.17 1,71,21 8.43
SRSF 177,22,48 127,20,30 -50,02,18 -28.23 74,62,15 42.11
OLWR 55,46 259,59 204,13 368.07 25,78 46.49
  Total 995,42,66 1171,15,84 ######## 18.13 543,11,84 54.56